Bloomsbury Quarter Construction: September 2025 Phase Two Update 

Dear Neighbour, 

With Phase One of the Sicilian Avenue redevelopment now complete, comprising 21 Southampton Row and Vernon House & Sicilian House, the premises are being marketed as prime office and retail spaces. Phase Two of the project at 31 Southampton Row commenced in early May 2025 and is advancing well. 

Phase Two Construction Update 

Construction remains on programme with several key milestones recently achieved. Recent highlights can be seen below: 

  • Demolition and internal strip-out: Soft strip is complete, with minor snagging underway. Demolition of floors one to four is complete; ground-floor demolition has started and is progressing steadily 

  • Scaffolding and hoarding: Perimeter scaffolding continues to rise along Vernon Place and Southampton Row. Installation of hoarding to the scaffold is scheduled for the week commencing 15 September to secure the site boundary and improve the street-facing appearance 

  • Drainage and building services: Below-ground drainage works are underway, with excavation and installation of the main drainage run in progress as part of the wider services upgrade 

  • Roof works: Demolition to form the opening at Staircase 1 is ongoing. The process of replacing slate, felt and battens on the Sicilian Avenue roof is underway. A condition survey of the rooflights has been completed, and a test area of the vapour control layer has been installed and approved 

  • Façade restoration: A review of the grand cornice with the client team took place on 4 September. Window restoration has begun on Level 4, and a benchmark window sample is ready for review by the design team. Scaffolding now reaches Level 3 on both Vernon Place and Southampton Row, enabling façade cleaning and repairs to commence 

  • Looking ahead: Demolition and façade works will continue throughout September. Structural assessments will progress with the project engineers. Roof works and window restoration will accelerate as full scaffold access becomes available across all elevations. 

For a glimpse of our latest on-site activity, please see the photos below.

Construction Meetings 

Due to low attendance, we have discontinued quarterly meetings; to request a progress briefing, please contact the team by emailing hello@bloomsburyquarterconstruction.co.uk or call 0800 772 0475. 

General Working Hours: 

In line with Camden Council policy, our normal working hours are: 

  • Monday to Friday, 8am – 6pm 

  • Saturday, 8am – 1pm 

  • No works will be undertaken on Sundays or public holidays. 

Emergency Contact Details: 

  • Jim Tipple, Project Director: 0752 218 5666 

We will be distributing monthly newsletters by email and providing regular updates on our website: www.bloomsburyquarterconstruction.co.uk. We recommend that you subscribe to our project emails to stay updated and to receive invitations to upcoming construction meetings. 

Should you have any questions or require additional information, please don't hesitate to get in touch by calling our freephone number: 0800 772 0475 or email us at hello@bloomsburyquarterconstruction.co.uk

Best wishes, 

Bloomsbury Quarter Construction Team 